Mr. Ryall then broke the Champagne bottle and Mr.
Chow switched on the TBM cutterhead.
Chi Ma Wan Tunnel, is part of CLP Power's improvement program for
the electric supply to Cheung Chau. The work involves boring a tunnel
that is 3.3 diameter, 3200m long for the placement of high voltage
cables, where environmental and ecology concerns are prime in consideration
of all methods employed.
The journey of Mu, Guiying is expected to take
about 10 months. Good luck to CLP Projects.
For more information, please contact
Susanna Poon
Communication Officer
Dragages Hong Kong
Tel: 2507 1730
Fax: 2588 1979
Email: susanna.poon@bouyguesasia.com
|