 |
 |
Partnering at the MTR Tseung Kwan
O Extension Hang Hau Station project.
How this approach saved money, shortened the
programme ... and led to a 'win win' situation for client and contractor. |
 |
When the MTR Corporation
proposed introducing a Partnering charter for the Hang Hau station
project, part of the MTRC Tseung Kwan O extension, Dragages
was delighted to accept. This meant approaching the project
in a spirit of co-operation and mutual understanding and with
four key objectives: to have structured and open communication
lines; to identify mutually beneficial goals; to streamline
administrative processes; and to solve problems promptly and
at the lowest possible level.
|
 |
 |
|
 |
| The benefits of Partnering became clear right at the
start of the project when Dragages proposed an alternative. The company's
'top-down' method for construction of the station was not included
in the contract at the time of the award, and a further design alternative
was required to make it acceptable to the MTRC and for it to work
as efficiently as possible. |
 |
| "Despite the feeling that such a major change
could jeopardise the tight programme for concreting works" explains
Dragages Project Director Bernard Senouci, "The MTRC agreed to
look at it. They agreed it was feasible and approved it. This kicked
off the project in a win-win spirit and we kept this spirit throughout
the project in all aspects including safety, quality and production".
|
 |
| MTRC Project Director, Russell Black, agrees: "We
have seen savings of several million dollars, which we can directly
attribute to partnering ... Dragages' suggestions accounted for much
of the savings which will now be split between the MTRC and the contractor.
It also cut construction time by five weeks." |
 |
Kenny Kong, Construction
Manager with the MTRC for the project cites a specific example
of how Partnering helped production: "We saw that the late
possession of a certain area would delay part of the contractor's
work. So we had long discussions with Dragages, the government
and the government's contractor. We all came to a solution whereby
the MTRC would take over the area at a later stage while Dragages
started some works in other areas. We reached a win win situation
for the government, ourselves and the contractor".
Dragages Contract Manager, John Edwards, says that Partnering
also enabled an innovative concept for controlling costs - a
Target Cost Incentive Mechanism: "With this mechanism a
sum was agreed between Dragages and the MTRC for defined potential
changes. Whatever remains unspent upon completion of the contract
is shared 50/50 between client and contractor".
|
 |
 |
|
| In all aspects of the project, Partnering has proved
its worth. "It is the way of the future for our business"
says Mr Senouci. |
 |
|
|
 |
 |